They certainly have played a waiting game Steve

They originally applied for planning in 2006 and were granted planning forabout 25 apartments but the condition was that the new side extensions could be demolished but the centre and original section was to remain
They demolished the side sections and then waited until their wilful neglect of the property meant that it was not "viable" to keep the centre section so they applied to demolish the centre section and build 28 apartments and that was granted. By the way the plans for the 28 apartments looked good and in keeping with the original building and surroundings
The centre section was quickly demolished and they waited and waited and waited and by 2013 they had alleged that work had commenced on the building by the fact that a pipe had been laid into the site!
Then they waited and waited and now appear to be talking to CCBC about a new plan that looks like something from Legoland and the apartments have increased from 28 to about 50
The last photo is of a painting by Dean Liddell who had the Penmorfa House built